Past Projects

A team you can trust.

Kaministiquia River at Hwy 61

LTL Directional Drilling supplied and installed 400m of 750mm dia. HDPE DR11 across the Kaministiquia River at Hwy 61.

They utilized a Vermeer 15-*300 directional drill with a 6000 gal mud recycler and a 600gpm mud pump. This project required 10 days of consecutive drilling with pullback pressures reaching a maximum 169,000 lbs. through a sand seam. The final hole opened up with a 36″ dia. fly-cutter reamer. The weight of the product pipe being installed was approximately 121,000 lbs.

Project Summary

750mm Watermain

Client:
City of Thunder Bay

Services Provided:

Pipe Installation

View All Projects