LTL constructed a new 2 cell sludge lagoon complete with lagoon outlet structures and forcemain inlet piping. Work performed included:
- excavation;
- backfilling; and
- site grading.
Significant drilling and blasting operation including Hoe-ram work was required to prepared site for pipe installations. We also constructed a new 11m x 10m sheet pile pump platform system in tailing pond with 40 ft long sheet piles and dywidag tie rod system.